When is a Sprint over?

1) When the time-box expires
2) When the Product Manager says so
3) When the Scrum Master says so
4) When the Sprint Backlog is all developed

User WhiteOne
by
7.9k points

1 Answer

6 votes

Final answer:

A Sprint is over when the time-box expires.

Step-by-step explanation:

A Sprint is over when the time-box expires. In Scrum, a time-boxed iteration is called a Sprint. The length of a Sprint is typically between one to four weeks and is determined by the Scrum Team. At the end of the time-box, the Sprint is considered over, regardless of the completion status of the Sprint Backlog.