What should they consider in setting the time-box for Sprints?

1) The amount of risk that increases by longer durations
2) The limitations in delivery of items that increases by shorter durations
3) Not more than one calendar month
4) All of the above

User Dan Levin
by
8.6k points

1 Answer

1 vote

Final answer:

When setting the time-box for Sprints in project management, factors such as risk, delivery limitations, and duration need to be considered.

Step-by-step explanation:

In setting the time-box for Sprints in project management, there are several factors to consider:

  1. The amount of risk that increases by longer durations: Longer sprints may increase the risk of unforeseen issues or changes in requirements that could disrupt the project.
  2. The limitations in delivery of items that increases by shorter durations: Shorter sprints can put pressure on the team to deliver smaller increments of work within a shorter timeframe, which may be challenging.
  3. Not more than one calendar month: Sprints are typically time-boxed to a maximum duration of one month to ensure regular feedback and progress.

All of the above factors should be considered when setting the time-box for Sprints to balance the need for risk management, efficient delivery, and a reasonable timeframe.