When the project exceeds previously determined timelines or resources, it is called

a) Overextension
b) Mismanagement
c) Scope creep
d) Bottlenecking

1 Answer

2 votes

Final answer:

The correct answer is c) scope creep. It refers to the tendency for a project to gradually expand beyond its original objectives or requirements.

Step-by-step explanation:

The correct answer is Scope creep. Scope creep refers to the tendency for a project to gradually expand beyond its original objectives or requirements. This can occur when additional features or changes are added to the project without adjusting the timelines or resources accordingly.

For example, let's say a software development project was initially planned to include basic functionality. However, as the project progresses, the client requests additional features, causing the project to exceed its original scope and timeframe.

Scope creep can be problematic as it can lead to delays and cost overruns. It is important for project managers to actively manage scope and communicate any changes or additions to stakeholders.