When using the plan-to-study (PDSA) process, which of the following occurs during the "plan" phase?

A. Determine how to collect data
B. Train staff on the new process
C. Evaluate the effectiveness of the project
D. Reduce wait time for appointments

1 Answer

4 votes

Final answer:

In the PDSA process, the 'plan' phase involves determining how to collect data, setting objectives, and developing a plan of action.

Step-by-step explanation:

During the "plan" phase of the Plan-Do-Study-Act (PDSA) process, the primary task is A. Determine how to collect data. This phase involves setting objectives, defining the scope of the project, and developing a detailed plan of action, which includes determining the data collection methodology that will be used to assess the project's effectiveness. It's important to have clear timelines and obtain buy-in from all stakeholders to ensure a smooth planning process. The planning phase is critical for laying the foundation for a successful project and includes making hypotheses about the outcomes.

User Aashitvyas
by
8.6k points