224k views
0 votes
40 men can catch 200 crabs in 20 days working 6 hours a day. In how many days can 25 men catch 300 crabs working 4 hours a day?

a. 25 days
b. 30 days
c. 35 days
d. 40 days

User Madbird
by
7.2k points

1 Answer

2 votes

Final answer:

To solve this work and time problem, the initial calculation of work hours and crab catching rate was correct, but the total hours needed by 25 men to catch 300 crabs working 4 hours a day was incorrectly compared to the options provided, which led to the discovery of an error in the options since none matched the correct calculation of 72 days.

Step-by-step explanation:

The problem you've presented is one of work and time, specifically involving proportions and rates. To solve it, we need to establish the rate at which the men catch crabs and then use this information to determine how many days it would take a different number of men, working for fewer hours, to catch a different number of crabs.

First, we calculate the total number of work hours in the original scenario: 40 men × 20 days × 6 hours/day = 4800 work hours. We then divide the total number of crabs by total work hours to find the rate: 200 crabs / 4800 work hours = 1 crab per 24 work hours.

In the new scenario, we want 25 men to catch 300 crabs. To find the total number of work hours needed, we multiply the desired number of crabs by the work hour rate: 300 crabs × 24 work hours/crab = 7200 work hours. Now, we divide the total number of work hours by the number of men and the number of hours they work each day to find the number of days: 7200 work hours / (25 men × 4 hours/day) = 72 days.

However, we must have made a mistake because 72 days is not one of the options provided (a. 25 days b. 30 days c. 35 days d. 40 days). Let's recheck our calculations. We initially calculated the work hours and the crab catching rate correctly. However, we should have divided the total hours required in the new scenario by the daily work hours of the new team, which is 100 work hours per day (25 men × 4 hours/day).

The correct number of days 25 men will take to catch 300 crabs working 4 hours a day will therefore be 7200 work hours / 100 work hours/day = 72 days. It seems there is an error in the provided options, as 72 days is not listed.

User Tevis
by
8.0k points