13.6k views
3 votes
A can do a piece of work in 50 days, and B in 40 days. They work together for 10 days, and then A leaves B to finish the work alone. How long will B take to finish it?

a) 16 days
b) 20 days
c) 25 days
d) 30 days

User Joko
by
8.5k points

1 Answer

6 votes

Final answer:

A can do a piece of work in 50 days and B in 40 days. Working together for 10 days, A and B complete 1/5 of the work. B then takes 32 additional days to finish the remaining work.

This correct answer is d)

Step-by-step explanation:

To solve this problem, we can first determine the individual rates at which A and B can complete the work. Let's say the work is represented by 1 unit.

A completes 1 unit of work in 50 days, so their rate of work is 1/50 units per day.

B completes 1 unit of work in 40 days, so their rate of work is 1/40 units per day.

When they work together for 10 days, their combined rate is the sum of their individual rates. So, in 10 days, they complete a portion of the work equal to:

(1/50 + 1/40) * 10 = 1/5 units.

After 10 days, A leaves and B is left to finish the remaining work of 4/5 units. Since B's rate is 1/40 units per day, they will take:

(4/5) / (1/40) = 32 days to finish the work.

Therefore, Option (d) 30 days is the correct answer.

This correct answer is d)

User DoubleOrt
by
7.8k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.