Final answer:
A, B, and C can complete the work separately in 18, 36, and 24 days respectively.
Step-by-step explanation:
To solve this problem, let's assign the following variables:
A = the amount of work A can do in 1 day
B = the amount of work B can do in 1 day
C = the amount of work C can do in 1 day
From the given information, we can form the following equations:
1) A + B + C = 1/12 (since they can complete the work together in 12 days)
2) A + C = 2(B) (A and C together work twice as much as B)
3) A + B = 3(C) (A and B together work thrice as much as C)
Solving these equations, we can find the values of A, B, and C:
A = 18, B = 36, C = 24
Therefore, each person can complete the work separately in the following times:
A: 18 days
B: 36 days
C: 24 days