64.7k views
0 votes
There are three workers A, B, and C. A takes thrice as much time as B and C together to do a task. B takes twice as much time as A and C together to do the task. If working together, the three of them require 10 hours to complete the task, then in how many days will C complete the task working 6 hours a day?

A) 20 days
B) 25 days
C) 30 days
D) 35 days

1 Answer

3 votes

Final answer:

After establishing the work rates for A, B, and C using the given relationships, solving the equations shows that worker C would require 30 days to complete the task, working 6 hours a day. Option C is correct.

Step-by-step explanation:

The student is asking about work rate problems in mathematics, specifically involving the time taken by individuals working together and alone on a particular task. To find out how many days worker C would require to complete the task working 6 hours a day, we first need to establish the work rates of A, B, and C. Using the information given, we set up the following relationships:

A's work rate is one-third the combined rate of B and C.

B's work rate is one-half the combined rate of A and C.

A, B, and C together work at a rate that takes 10 hours to complete the task.

Next, we denote the individual work rates of A, B, and C as 1/A, 1/B, and 1/C respectively, and the combined work rate as 1/10 since they complete the task in 10 hours. Therefore, we get the following equations based on the relationships:

1/A = 1/(B + C)

1/B = 1/(A + C)

1/A + 1/B + 1/C = 1/10

By solving these equations, we can find the individual work rate of C. We then calculate the time that C would take to complete the task and convert this time into days, considering C works 6 hours a day. Through this method, we can determine that C would take 30 days to complete the task (Option C).

User Kung
by
7.9k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.