115k views
0 votes
Team one needs 5 days to finish the project by themselves, team two needs 6 days to finish it by themselves. If the two teams work together, how many days are needed?

a) 2.4 days
b) 2.5 days
c) 2.6 days
d) 2.7 days

User Mmtauqir
by
7.6k points

1 Answer

4 votes

Final answer:

When team one and team two work together, they have a combined rate of (11/30) of the project per day, which means they would complete the project in approximately 2.73 days, with the nearest answer choice being 2.7 days.

Step-by-step explanation:

To calculate the total time needed for two teams working together, we can use the rates at which each team works. Team one completes the project in 5 days, which means their rate of work is 1 project per 5 days, or 1/5 of the project per day. Team two completes the project in 6 days, meaning their rate is 1 project per 6 days, or 1/6 of the project per day. When they work together, their combined rate is 1/5 + 1/6 per day. To find this sum, we need a common denominator, which in this case is 30 (5 × 6).

Combining the rates of the two teams gives us (6/30) + (5/30) = (11/30) of the project per day. To find the total number of days (D) needed to complete one entire project working together at this combined rate, we set up the equation D × (11/30) = 1. Solving for D gives us D = 30/11, which is approximately 2.73 days. Thus, the closest answer is d) 2.7 days.

User Shanikah
by
8.1k points