Final answer:
The correct answer is A. Project manager has full authority. A pure project is a type of organizational structure in which a project manager has full authority and control over the resources allocated to the project.
Step-by-step explanation:
The correct answer is A. Project manager has full authority.
A pure project is a type of organizational structure in which a project manager has full authority and control over the resources allocated to the project.
While this can be an advantage in terms of decision-making and accountability, it may also lead to challenges such as conflicts with other departments and lack of coordination with organizational goals.
In contrast, the advantages of a pure project include team members working on one project, shortened communication lines, and increased flexibility in resource use.