Final answer:
The correct order of the phases of project management is Planning, Execution, Monitoring, and Closing, providing a systematic approach from start to finish.
Step-by-step explanation:
The phases of project management typically follow a standardized sequence to ensure the project is completed efficiently and effectively. The appropriate order for these phases is:
- Planning
- Execution
- Monitoring (and Controlling)
- Closing
This sequence ensures that a project is well-organized from the outset, implemented according to the plan, regularly checked for alignment with objectives, and properly closed and reviewed upon completion. Consequently, the correct answer to the student's question is a) Planning, Execution, Monitoring, Closing.