196k views
0 votes
Assign tasks to workstations on the basis of the greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

A. Johnson's Rule
B. Critical Path Method (CPM)
C. PERT (Program Evaluation and Review Technique)
D. Kanban System
E. None of the above

User MSajjadi
by
7.6k points

1 Answer

4 votes

Final answer:

Johnson's Rule is used to assign tasks to workstations based on the greatest number of tasks, using the longest processing time as a tiebreaker.

Step-by-step explanation:

In the context of assigning tasks to workstations based on the greatest number of tasks, Johnson's Rule is commonly used. It involves scheduling tasks in a way that minimizes idle time and maximizes efficiency. The tiebreaker is the longest processing time, which means that tasks with longer completion times are given priority.

For example, let's say we have three tasks: Task A, Task B, and Task C, with completion times of 4 hours, 3 hours, and 6 hours, respectively. According to Johnson's Rule, the tasks would be assigned in the following order: Task B (3 hours) - Task A (4 hours) - Task C (6 hours).

This process ensures that tasks are assigned in a way that optimizes throughput and reduces overall completion time.

User Gabriel Glauber
by
8.9k points