174k views
1 vote
Sussex Company uses a standard cost system and prepared the following budget for May when 24,000 machine hours of activity were anticipated: variable overhead, $48,000; fixed overhead: $240,000. Actual data for May were:

Standard machine hours allowed for output attained: 25,000

Actual machine hours worked: 24,000

Variable overhead incurred: $50,000

Fixed overhead incurred: $250,000

44. The standard variable overhead rate for May is:

A. $2.00.

B. $2.08.

C. $3.00.

D. $5.00.

E. $5.21.




The variable-overhead spending and efficiency variances are:

Variable-Overhead Spending Variance
Variable-Overhead Efficiency Variance

A. $0 $0

B. $0 $2,000 unfavorable

C. $2,000 unfavorable $0

D. $2,000 favorable $2,000 unfavorable

E. $2,000 unfavorable $2,000 favorable


46. The fixed-overhead budget and volume variances are:

Fixed-Overhead Budget Variance
Fixed-Overhead Volume Variance

A. $0 $10,000 favorable

B. $10,000 favorable $0

C. $10,000 favorable $10,000 unfavorable

D. $10,000 unfavorable $0

E. $10,000 unfavorable $10,000 favorable

User Swiesend
by
7.3k points

1 Answer

3 votes

Final answer:

The standard variable overhead rate for May is $1.92. The variable-overhead spending variance is $2,000 unfavorable, and the variable-overhead efficiency variance is $2,000 favorable. The fixed-overhead budget variance is $10,000 unfavorable, and the fixed-overhead volume variance is $10,000 unfavorable.

Step-by-step explanation:

The standard variable overhead rate for May can be calculated by dividing the budgeted variable overhead by the standard machine hours allowed for output attained. In this case, the budgeted variable overhead is $48,000 and the standard machine hours allowed for output attained is 25,000. Therefore, the standard variable overhead rate for May is:



$48,000 / 25,000 = $1.92



Hence, the correct answer choice is option A. $2.00 is the closest option to $1.92, so it is the standard variable overhead rate for May.



The variable-overhead spending variance can be calculated by subtracting the actual variable overhead incurred from the budgeted variable overhead. In this case, the budgeted variable overhead is $48,000 and the actual variable overhead incurred is $50,000. Therefore, the variable-overhead spending variance is:



$48,000 - $50,000 = -$2,000



The variable-overhead efficiency variance can be calculated by multiplying the standard variable overhead rate by the difference between the standard machine hours allowed for output attained and the actual machine hours worked. In this case, the standard variable overhead rate is $1.92 (or $2.00) and the difference between the standard machine hours allowed for output attained and the actual machine hours worked is 25,000 - 24,000 = 1,000. Therefore, the variable-overhead efficiency variance is:



$1.92 (or $2.00) × 1,000 = $1,920 (or $2,000)



Hence, the correct answer choice is option D. $2,000 favorable is the closest option to $1,920 (or $2,000) favorable, so it is the variable-overhead efficiency variance.



The fixed-overhead budget variance can be calculated by subtracting the budgeted fixed overhead from the actual fixed overhead incurred. In this case, the budgeted fixed overhead is $240,000 and the actual fixed overhead incurred is $250,000. Therefore, the fixed-overhead budget variance is:



$240,000 - $250,000 = -$10,000

The fixed-overhead volume variance can be calculated by multiplying the standard fixed overhead rate by the difference between the standard machine hours allowed for output attained and the actual machine hours worked. In this case, the standard fixed overhead rate is:

(Budgeted fixed overhead + Fixed-overhead budget variance) / Standard machine hours allowed for output attained
= ($240,000 + -$10,000) / 25,000
= $230,000 / 25,000
= $9.20

The difference between the standard machine hours allowed for output attained and the actual machine hours worked is 25,000 - 24,000 = 1,000. Therefore, the fixed-overhead volume variance is:

$9.20 × 1,000 = $9,200

Hence, the correct answer choice is option E. $10,000 unfavorable is the closest option to $9,200 unfavorable, so it is the fixed-overhead volume variance.

User Bokris Itzhak
by
8.0k points