Final answer:
The flexible budget for Lantern Corporation's 60,000 units of production should be $370,000. Actual costs were $367,000, which implies that the total variance is $3,000 favorable. Therefore, the correct answer is A. $3,000 favorable.
Step-by-step explanation:
To determine the total variance, we will first create a flexible budget based on actual production and then compare it to actual costs. Here's how you do it:
The flexible budget for production of 60,000 units will show that the company should have incurred:
The total of these figures is $370,000. The actual cost incurred was $110,000 + $60,000 + $100,000 + $97,000 = $367,000. Subtract the actual costs from the flexible budget to find the total variance:
Variance = $370,000 (Flexible Budget) - $367,000 (Actual Costs) = $3,000
Since the actual costs were less than the flexible budget, the variance is favorable. Therefore, the correct answer is A. $3,000 favorable.