A regenerative MRP system is one that is updated continuously - every time there is a schedule change

A) Verified
B) Debunked
C) Speculated
D) Discarded

1 Answer

6 votes

Final answer:

The statement about a regenerative MRP system being updated continuously is debunked; regenerative MRP systems are updated at specific intervals and not continuously.

Step-by-step explanation:

A regenerative MRP system is one that is completely updated at certain intervals, rather than continuously. Typically, all records are cleared and then updated to reflect the latest data. So, the statement that a regenerative MRP system is updated continuously — every time there is a schedule change — is Debunked. Instead, a net change MRP system is the type that updates continuously as new information becomes available. A regenerative system updates the material requirements planning at specific intervals, which can be on a weekly or monthly basis, or at any other scheduled times.