Final answer:
The 'Command and control the project team' option does not align with the ANSI/PMI 99-001-2021 project delivery principles, which favor a collaborative approach over rigid control.
Step-by-step explanation:
The option that does NOT reflect one of the twelve delivery principles defined by the Standard for Project Management ANSI/PMI 99-001-2021 is 'Command and control the project team'. The principles included in the standard emphasize a more collaborative and flexible approach to project management. Some of the core principles are to tailor your delivery approach, to focus on value, and to effectively engage with stakeholders. Commanding and controlling the project team would contradict the more modern, adaptive, and inclusive project management methods that are recommended by the standard.