127k views
0 votes
All of these are causes of project failure EXCEPT: inadequate user involvement.

complete, clear requirements.
unrealistic expectations.
inadequate planning.

User SimonAx
by
7.9k points

1 Answer

1 vote

Final answer:

Unrealistic expectations is not a cause of project failure.

Step-by-step explanation:

The given options are:
(1) Inadequate user involvement
(2) Complete, clear requirements
(3) Unrealistic expectations
(4) Inadequate planning


The question is asking which of these options is NOT a cause of project failure.

To identify the correct answer, we need to consider which option is actually a cause of project failure. Inadequate user involvement, complete, clear requirements, and inadequate planning are all factors that can contribute to project failure.

However, unrealistic expectations are not listed as a cause of project failure, so the correct answer is (3) Unrealistic expectations.

User Charmi Gheewala
by
9.2k points