Final answer:
Hiring two experienced workers and one trainee would take approximately 26 2/3 days to complete the project, not 11 1/2 days.
Step-by-step explanation:
To solve this problem, we can assign rates of work to each worker. Let's say the rate of work for an experienced worker is x projects per day and the rate of work for a trainee is y projects per day.
From the given information, we can set up the following equations:
2x + 3y = 1/10 (Equation 1)
3x + 2y = 1/8 (Equation 2)
Solving these two equations, we find that x = 1/40 and y = 1/80.
Now, let's calculate the combined rate of work for two experienced workers and one trainee:
(2 * 1/40) + (1 * 1/80) = 1/20 + 1/80 = 3/80 projects per day.
Using the combined rate of work, we can calculate the number of days it would take for them to complete the project:
(1 project) / (3/80 projects per day) = 80/3 days = 26 2/3 days.
Therefore, hiring two experienced workers and one trainee would take approximately 26 2/3 days to complete the project, not 11 1/2 days.