The scope baseline is an output of what process?

1) Plan scope management
2) Define scope
3) Collect requirements
4) Create WBS

User CPBL
by
8.1k points

1 Answer

3 votes

Final answer:

The scope baseline is an output of the Create WBS (Work Breakdown Structure) process in project management.

Step-by-step explanation:

The scope baseline is a key component within project management that outlines the project's scope, including project deliverables and the work required to complete those deliverables. It is an output of the process known as Create WBS (Work Breakdown Structure). The scope baseline consists of the project scope statement, the WBS, and the WBS dictionary.



To clarify the design process in engineering, the last step typically involves Communicate process and results, while the first step is to Define the problem. Throughout the design process, criteria and constraints must be considered, and it's important to continuously refine the design and test and evaluate it before it can be considered a good design, regardless of the size of the engineering firm involved.

User Elltz
by
7.4k points