Which statement about the deliverables is most accurate?

1) Deliverables are created through the scope processes
2) Deliverables are evaluated through the validate scope process prior to final review during the control quality process
3) Deliverables are verified once they have gone through the control quality process
4) Accepted deliverables will be provided to the requesting party for verification in the validate scope process.

1 Answer

4 votes

Final answer:

The correct statement about deliverables is that they are evaluated through the validate scope process before final review in the control quality process, in line with the iterative and quality-focused nature of the engineering design process.

Step-by-step explanation:

The most accurate statement about deliverables is that they are evaluated through the validate scope process prior to the final review during the control quality process. This is in line with standard project management practices where the focus is to make sure that the deliverables meet the acceptance criteria set out in the project scope. It's important in the engineering design process to ensure that each deliverable goes through an iterative process of planning, implementing, testing, evaluating, and refining to achieve the desired quality.

In the context of the engineering design process, deliverables would be tested and evaluated as the last step in the design process, often involving iterating phases such as prototyping, testing, evaluating, and refining. This spiraling or iterative approach allows engineers to continually improve the design based on feedback and testing results, leading to a good design that meets all the set criteria and constraints.

Following iterative testing and refinement, the deliverables would then be verified for quality before being handed over to the requesting party, which showcases the importance of both iterative development and thorough validation in engineering.