Which of the following is not a component of the scope baseline?

1) Scope statement
2) Work breakdown structure
3) Scope deliverables
4) Work breakdown structure dictionary

User Neptali
by
7.6k points

1 Answer

0 votes

Final answer:

The scope baseline in project management includes the scope statement, work breakdown structure, and work breakdown structure dictionary, but not scope deliverables.

Step-by-step explanation:

The scope baseline in project management consists of three components: the scope statement, the work breakdown structure (WBS), and the work breakdown structure dictionary. The scope statement defines the project's objectives, deliverables, and boundaries. The WBS breaks down the project into smaller, manageable tasks, and the dictionary provides detailed information about each task in the WBS.

The scope deliverables mentioned in the question are part of the scope baseline. They are the products, services, or results that the project aims to deliver to meet its objectives.

Therefore, the correct answer is 3) Scope deliverables as it is not a component of the scope baseline in project management.