The project is estimated to have a 12,500 variance at completion. The project budget is 75,000 and the estimate to complete the remaining work is 15,750. What are the actual costs of the project to-date?

1) Unable to determine
2) 59,250
3) 62,500
4) 46,750

User Cheila
by
8.8k points

1 Answer

4 votes

Final answer:

The actual costs of the project to-date can be found by subtracting the estimate to complete the remaining work from the project budget. In this case, the actual costs are $59,250.

Step-by-step explanation:

The actual costs of the project to-date can be found by subtracting the estimate to complete the remaining work from the project budget. In this case, the project budget is $75,000 and the estimate to complete the remaining work is $15,750. Therefore, the actual costs of the project to-date are $59,250.

User Myrna
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories