Final answer:
The actual costs of the project to-date can be found by subtracting the estimate to complete the remaining work from the project budget. In this case, the actual costs are $59,250.
Step-by-step explanation:
The actual costs of the project to-date can be found by subtracting the estimate to complete the remaining work from the project budget. In this case, the project budget is $75,000 and the estimate to complete the remaining work is $15,750. Therefore, the actual costs of the project to-date are $59,250.