What is the annual fixed cost and annual capacity of the proposed plants in Detroit, Toledo, Denver, and Kansas City?

1) 175,000 and 40,000
2) 300,000 and 10,000
3) 375,000 and 20,000
4) 500,000 and 30,000

User Bradley D
by
7.5k points

1 Answer

1 vote

Final answer:

The annual fixed cost and annual capacity of the proposed plants in Detroit, Toledo, Denver, and Kansas City are given.

Step-by-step explanation:

The annual fixed cost and annual capacity of the proposed plants in Detroit, Toledo, Denver, and Kansas City are as follows:

  1. Plant in Detroit: Annual fixed cost of $175,000 and annual capacity of 40,000
  2. Plant in Toledo: Annual fixed cost of $300,000 and annual capacity of 10,000
  3. Plant in Denver: Annual fixed cost of $375,000 and annual capacity of 20,000
  4. Plant in Kansas City: Annual fixed cost of $500,000 and annual capacity of 30,000

User Jarek
by
7.7k points