What is the term used for shortening activity durations?

1) Crashing
2) Fast tracking
3) Resource leveling
4) Schedule compression

1 Answer

6 votes

Final answer:

Schedule compression is the term used for shortening activity durations in project management.

Step-by-step explanation:

The term used for shortening activity durations in project management is Schedule compression. Schedule compression refers to the techniques used to reduce the project schedule without changing the project scope. There are two common techniques of schedule compression which are crashing and fast-tracking.