Once a project is authorized and/or a contract is signed with an external contractor, the next phase of the project life cycle is to do detailed __________ for how to accomplish the project.

A. Design
B. Planning
C. Execution
D. Evaluation

User Nemostyle
by
7.7k points

1 Answer

3 votes

Final answer:

The correct option is (B). The next phase of the project life cycle is planning, which involves developing a detailed design for how to accomplish the project.

Step-by-step explanation:

The next phase of the project life cycle, after a project is authorized and/or a contract is signed with an external contractor, is planning.

Planning involves developing a detailed design for how to accomplish the project. This includes identifying physical and functional components, determining shapes and dimensions, selecting materials and fabrication processes, and identifying product components. A detailed design is necessary to ensure that the project is executed effectively and efficiently, and to avoid potential issues or failures.