In MS Project, the view that exhibits the network diagram is the _______.

A) Resource sheet
B) PERT chart
C) Gantt chart
D) Task sheet

1 Answer

5 votes

Final answer:

In MS Project, the view that exhibits the network diagram is the B) PERT chart. This chart is used in project management to analyze task durations and dependencies. Other views like the Gantt chart, Resource Sheet, and Task Sheet offer different types of project information presentation.

Step-by-step explanation:

In MS Project, the view that exhibits the network diagram is the B) PERT chart. The Program Evaluation and Review Technique (PERT) chart is used for project management and is designed to analyze the tasks involved in completing a given project, particularly the time needed to complete each task, and to identify the minimum time needed to complete the total project.

The Gantt chart is another type of view in MS Project that represents project tasks along a timeline but does not display the network diagram of task dependencies as a PERT chart does. Instead, it's a bar chart that provides a visual overview of the project schedule. The Resource Sheet is a different view focused on listing the resources for the project and their details. Lastly, the Task Sheet is a tabular view that lists all the tasks along with their details but without graphical representation.

User Cmutex
by
6.6k points