All of the following are traditional project management techniques for scheduling and planning except:

A) CPM
B) PLAN
C) Gantt Chart
D) PERT

User Truong Ha
by
8.0k points

1 Answer

1 vote

Final answer:

The correct answer to the question 'Which of the following is not a traditional project management technique for scheduling and planning?' is B) PLAN. CPM, Gantt Charts, and PERT are well-established techniques used for project management that focus on scheduling and planning.

Step-by-step explanation:

The traditional project management techniques for scheduling and planning include the Critical Path Method (CPM), the Gantt Chart, and the Program Evaluation Review Technique (PERT). Among the options provided, A) CPM, C) Gantt Chart, and D) PERT are well-known and established techniques for project planning and scheduling. B) PLAN is not generally recognized as a standard project management technique in the context of the provided options, thus it is the correct answer to the question.

CPM is a step-by-step project management technique that identifies critical and non-critical tasks to prevent time-frame problems and process bottlenecks. A Gantt Chart is a visual tool that displays the timeline of the project tasks alongside their duration. PERT is a method that uses a network diagram to analyze and represent the tasks involved in completing a given project, often with an emphasis on time needed to complete each task.