Final answer:
The total relevant cost of skilled labor for the order of 8 units of Product Delta is £540.
Step-by-step explanation:
The total relevant cost of skilled labour for the order can be calculated by multiplying the number of units of Product Delta by the time taken to make each unit and the cost of skilled labor per hour. According to the information provided, the time taken to make each unit decreases by one hour for each unit made. So, the total time taken to make 8 units can be calculated as follows:
- The time taken to make the first unit = 20 hours
- The time taken to make the second unit = 19 hours
- The time taken to make the third unit = 18 hours
- And so on...
The total relevant cost of skilled labor for the order can be calculated by summing up the cost of labor for each unit:
- For the first unit: £15 x 20 hours = £300
- For the second unit: £15 x 19 hours = £285
- For the third unit: £15 x 18 hours = £270
- And so on...
To find the total relevant cost of skilled labor:
Total cost = £300 + £285 + £270 + ...
This is an arithmetic series with a common difference of -1 and the first term of 300. Using the formula for the sum of an arithmetic series, the total relevant cost of skilled labor can be calculated as:
Total cost = (n/2)(2a + (n-1)d) = (8/2)(2(300) + (8-1)(-15)) = £540
Therefore, the total relevant cost of skilled labor for the order is £540.