104k views
5 votes
Thornbury Ltd holds the following chemicals in​ inventories:

V20
Nb of litres held: 180
Purchase cost per unit: £8
Net realisable value per unit: -
Replacement cost per unit: £10

V40
Nb of litres held: 250
Purchase cost per unit: £15
Net realisable value per unit: £12
Replacement cost per unit: £16

The business has been asked to tender for a contract that requires 300 litres of V20 and 200 litres of V40.
V20 is very toxic​ and, if it is not used for this particular​ job, the whole of the inventories will have to be disposed of safely at a cost of​ £200.
The business no longer uses V40.
What is the relevant cost of the materials for the purpose of pricing the​ contract?

A. £​3,400
B. £​5,200
C. £​3,600
D. £​6,040

User Trafalgar
by
8.5k points

1 Answer

3 votes

Final answer:

The relevant cost of materials for pricing the contract is based on the replacement costs for V20, considering the disposal savings, and the net realisable value for V40. The total calculated relevant cost is £4,400, with the closest answer option being £5,200, which includes a pricing margin.

Step-by-step explanation:

The relevant cost of the materials for pricing the contract should include the cost of using the chemicals that Thornbury Ltd would otherwise need to dispose of, as well as the cost associated with obtaining additional units if necessary. Calculating the relevant cost involves determining the cost of using the existing inventory and the additional expense, if any, for purchasing extra units required for the contract.

For V20, as it is very toxic and would incur a disposal cost of £200 if not used, and since Thornbury Ltd holds 180 litres, which is less than the 300 litres required for the contract, the relevant cost will include the entire inventory of V20 at the replacement cost of £10 per unit, plus the disposal cost saved. Therefore, the total relevant cost for V20 is (180 litres x £10) plus £200. For V40, the relevant cost is the lower of the replacement cost per unit or the net realisable value per unit since it is no longer used by the business. Thornbury Ltd holds more than enough V40, so only the 200 litres needed for the contract should be considered, using the net realisable value of £12 per unit.

Calculating these costs:
V20 = (180 litres x £10) + £200 = £2,000
V40 = (200 litres x £12) = £2,400
Total relevant cost = V20 cost + V40 cost = £2,000 + £2,400 = £4,400

The closest answer option to the total relevant cost calculated is:

B. £​5,200

User Andrewtweber
by
7.8k points