In MS Project, which button do you click for subordination?

A) Link
B) Indent
C) Resource assign
D) Resource sheet

User Solo
by
7.6k points

1 Answer

6 votes

Final answer:

In MS Project, to create a subordinate task, click on the Indent button in the Task Tab>Schedule group. This will make the selected task a subtask of the task above it, creating a hierarchical relationship between the tasks.

Step-by-step explanation:

In MS Project, to create a subordinate task, you click on the Indent button.

This button is located on the Task Tab in the Schedule group.

By clicking the Indent button, the selected task will become a subtask of the task above it, creating a hierarchical relationship between the tasks.