In MS Project, which button do you click on to indicate precedence?

A) Link
B) Indent
C) Resource assign
D) Resource sheet

User Wallacer
by
8.3k points

1 Answer

5 votes

Final answer:

In MS Project, the Link button is used to indicate precedence among tasks by creating dependencies between them, which is represented by the chain icon. This allows one task to start after the completion of another, establishing a task order.

Step-by-step explanation:

In MS Project, to indicate precedence among tasks, you would click on the Link button. Precedence refers to the order in which tasks need to be completed, with some tasks being dependent on the completion of others. To establish this relationship, you would select the tasks you want to link, usually by clicking on the first task and then holding the Ctrl key and clicking on the succeeding task, and then click the Link button (often represented by a chain icon). This creates a finish-to-start dependency by default, meaning the second task will start after the first task is complete. You can adjust these dependencies as needed by double-clicking on the link lines that appear on the Gantt Chart view and selecting different dependency types if required (finish-to-finish, start-to-start, or start-to-finish).

User Chengqi
by
8.3k points