Which of these may a Development team delivery at the end of a Sprint? Choose 2 answers

User SilverNak
by
7.9k points

1 Answer

1 vote

Final answer:

A Development Team in a Scrum framework is expected to deliver a potentially shippable product increment and updated Sprint backlogs at the end of a Sprint.

Step-by-step explanation:

The question pertains to the Scrum framework, a popular method used in agile software development. Specifically, it asks what a Development Team may deliver at the end of a Sprint. The two main deliverables are:

  • A potentially shippable product increment, which means the work done during the Sprint is potentially releasable and meets the team's definition of done.
  • Updated Sprint backlogs, reflecting what has been completed and what remains to be done for future Sprints.

These deliverables signify the progress of the project and ensure that the team has a clear understanding of what has been accomplished and what still needs to be done.