193k views
2 votes
In a dairy factory, 250 tons of raw milk per day is transported to the facility by trucks and via pipeline.

is transferred to storage tanks. The creation of a new pipeline for this purpose is being considered
and the optimum pipe diameter is tried to be decided.
The pump was placed in place of the truck tanker and the milk level of the raw milk truck tank was 8 m.
Feeding is done to the upper inlet of the storage tank in the cabinet. Two points in its atmosphere
within. The factory works 300 days a year, in a single shift (9 hours).
The entire pipeline consists of 70 m straight pipe, 5 90\deg standard elbows and 4 globe valves
occurs. (A design will be made using all of these materials.)
**Which prevalence of steel pipe use? (sch40 available)**
Additional Information:
1. The efficiency of the pump is 65%.
2. It will be structured as 1,2,3,4 and 5 inch steel pipes.
3. All materials supplied along the pipeline (straight pipe, elbow and valves)
Contains.
4. Milk line depreciation rate is 20%.
Design the pipeline system given above. This design is included in the content
what needs to be done,
1. Complete solution to the problem
2. Graphical presentation of cost analysis (Optimum economic design)
3. Drawing of the pipeline (correct placement of pipes, pumps, valves and elbows)
4. Resources

User Riva
by
8.0k points

1 Answer

5 votes

Final answer:

The problem requires an engineering design of an optimal pipeline system for transporting milk. A graphical cost analysis and a drawing of the pipeline layout are essential to the solution.

Step-by-step explanation:

To determine the appropriate prevalence of steel pipe to be used in the dairy factory's pipeline, we need to consider the flow rate of the milk and the pressure required for the pump to transfer the milk into the storage tanks. The flow rate can be calculated by applying Bernoulli's equation, which relates the velocity of the fluid to the pressure difference and the density of the fluid. The pressure required for the pump can be determined by considering the height difference between the pump and the storage tanks, as well as the friction losses in the pipeline.

By analyzing the given information about the pipeline, we can calculate the corresponding flow rate and pressure required. Then, we can use these values to determine the appropriate diameter of the steel pipe, taking into account the material properties and the desired flow rate. The economic design of the pipeline can be determined through cost analysis, considering the costs associated with the different pipe diameters and other components of the pipeline.

To provide a complete solution to the problem, we would need the specific values of the flow rate, pump efficiency, height difference, and other relevant parameters. Additionally, a graphical presentation of the cost analysis and a drawing of the pipeline would require more detailed information about the pipeline layout and component specifications.

User Memuna
by
7.3k points