The first build activity cannot start until the first design activity is completed in:

a. Traditional Project Delivery Method
b. Phased project delivery method
c. Fast trrack project delivery method
d. None of the above

User Edencorbin
by
7.4k points

1 Answer

5 votes

Final answer:

The first build activity cannot start until the first design activity is completed in the Traditional Project Delivery Method.

Step-by-step explanation:

In project management, the sequence of activities is determined by the project delivery method being used. In the traditional project delivery method, the first build activity cannot start until the first design activity is completed. This method follows a sequential order where each phase is completed before moving on to the next phase.

In contrast, both the phased project delivery method and the fast track project delivery method allow for overlap of activities. With the phased method, different phases of the project can be carried out simultaneously, while the fast track method involves starting certain activities before the completion of others.

Therefore, the correct answer is a. Traditional Project Delivery Method.