190k views
1 vote
Which of the following is not involved in the project management triangle?

A. Resources
B. Time
C. Efficiency
D. Scope

1 Answer

4 votes

Final answer:

C. Efficiency

Efficiency is not involved in the project management triangle.

Step-by-step explanation:

The project management triangle, also known as the triple constraint or iron triangle, is a concept used in project management to illustrate the trade-offs between three key project aspects: Time, Resources, and Scope. The fourth option, Efficiency, is not directly involved in the project management triangle. Efficiency can be seen as a desired outcome of managing the project successfully, but it is not one of the three factors that need to be balanced.

User Pathik Patel
by
8.2k points

No related questions found