Final answer:
The activities are to be scheduled using CPM. A, B, C, D, E, F, and G are the activities with their respective immediate predecessors and time in weeks.
Step-by-step explanation:
The subject of this question is Advanced Placement (AP) and the grade is High School.
The question is asking about the activities to be scheduled using CPM (Critical Path Method). CPM is a project management technique used to identify the critical activities that determine the overall duration of a project.
The given activities and their immediate predecessors, along with their respective time in weeks, are as follows:
- A has no immediate predecessor and takes 5 weeks.
- B has A as an immediate predecessor and takes 2 weeks.
- C has A as an immediate predecessor and takes 8 weeks.
- D has C as an immediate predecessor and takes 3 weeks.
- E has B and D as immediate predecessors and takes 5 weeks.
- F has D as an immediate predecessor and takes 2 weeks.
- G has E and F as immediate predecessors and takes 8 weeks.
Using this information, we can create a project schedule by analyzing the dependencies and determining the critical path, which represents the longest sequence of activities that cannot be delayed without delaying the entire project.