125k views
1 vote
A firm evaluates all of its projects by applying the NPV decision rule. A project under consideration has the following cash flows: Year Cash Flow 0 −$ 28,600 1 12,600 2 15,600 3 11,600 What is the NPV for the project if the required return is 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

At a required return of 11 percent, should the firm accept this project?
multiple choice 1
a.Yes
b.No

User Mari
by
8.3k points

1 Answer

2 votes

Final answer:

To determine if the project should be accepted, the NPV is calculated by discounting the future cash flows at an 11% required return. The NPV is found to be positive at $4,107.05, indicating that the firm should accept the project.

Step-by-step explanation:

To calculate the Net Present Value (NPV) of the project, we need to discount each of the future cash flows back to the present value using the required return of 11%. The formula for the present value of a future cash flow is:

Present Value = Future Cash Flow / (1 + r)^n

Where r is the required return and n is the number of periods until the cash flow is received.

  1. Calculate the present value for Year 1 cash flow: PV1 = 12600 / (1 + 0.11)^1 = $11,351.35
  2. Calculate the present value for Year 2 cash flow: PV2 = 15600 / (1 + 0.11)^2 = $12,703.60
  3. Calculate the present value for Year 3 cash flow: PV3 = 11600 / (1 + 0.11)^3 = $8,652.10

Next, we combine these with the initial investment to get the NPV:

NPV = -28,600 + PV1 + PV2 + PV3

NPV = -28,600 + 11,351.35 + 12,703.60 + 8,652.10

NPV = $4,107.05

Since the NPV is positive, at an 11 percent required return, the firm should accept the project as it expects to add value to the firm.

User Farrukh Waheed
by
8.4k points