Which of the following is least likely to be a test of a control?

a. Inquiries of appropriate personnel.
b. Inspection of management's engagement letter.
c. Observation of the application of a policy.
d. Reperformance of the application of a policy

User Xantium
by
9.1k points

1 Answer

4 votes

Final answer:

The least likely test of a control is the inspection of management's engagement letter because it does not assess control effectiveness but rather the agreement terms with management.

Step-by-step explanation:

The item least likely to be a test of a control is b. Inspection of management's engagement letter. A test of a control is used to verify the effectiveness of an internal control designed to prevent or detect errors and fraud. While inquiries of appropriate personnel, observation of the application of a policy, and reperformance of the application of a policy are all methods to test if the controls are functioning as intended, the inspection of management's engagement letter would not typically serve as a method to assess the operational effectiveness of internal controls. It might, instead, provide information about the terms and responsibilities agreed upon with management.