Slack time is equal to LS-ES or LF-EF.

True
False

User SavageGoat
by
8.7k points

1 Answer

2 votes

Final answer:

The statement that slack time is equal to LS-ES or LF-EF is true. Slack time refers to the delay a task can have without affecting the overall project timeline.

Step-by-step explanation:

The statement is true. Slack time, also known as float, is a concept in project management that refers to the amount of time a task in a project can be delayed without causing a delay to subsequent tasks or the project completion date. Slack time is indeed calculated by doing one of two things: subtracting the Early Start (ES) date of a task from the Late Start (LS) date, or subtracting the Early Finish (EF) date of a task from the Late Finish (LF) date. This results in either LS-ES or LF-EF, respectively. Therefore, if these calculations result in a positive number, there is slack time available for that specific task, and if it is zero or negative, the task is critical and must be completed on time.

User Amin Ba
by
8.8k points