2. Consider the following three jobs: Job Alpha requires two weeks of work and is due in four weeks. Job Beta requires three weeks of work and is due in five weeks. Job Carlos requires one week of work and is due in three weeks. If these jobs are completed in alphabetical order, how late will Job Beta be?

User Houston
by
7.9k points

1 Answer

5 votes

Final answer:

Job Beta will be completed two weeks late.

Step-by-step explanation:

If we complete the jobs in alphabetical order, Job Alpha would be completed first, followed by Job Beta, and then Job Carlos. Since Job Beta requires three weeks of work and is due in five weeks, it will be completed two weeks late.