It takes 7 swordsmiths 12 months to forge 100 swords. How many months will it take 2 swordsmiths to forge 300 swords?

User DappWind
by
8.2k points

1 Answer

7 votes

Final answer:

It will take 2 swordsmiths approximately 28.57 months to forge 300 swords.

Step-by-step explanation:

To find out how many months it will take 2 swordsmiths to forge 300 swords, we can set up a proportion using the ratio of swordsmiths to swords. Since it takes 7 swordsmiths 12 months to forge 100 swords, the ratio is 7:100. Let 'x' be the number of months it will take 2 swordsmiths to forge 300 swords. The ratio for 2 swordsmiths would be 2:x. Cross-multiplying, we get 7x = 200, and solving for 'x', we find that it will take 2 swordsmiths approximately 28.57 months to forge 300 swords.