Sparky knows that installing the new equipment and training workers to use it efficiently will be a long and complex process consisting of many different tasks. which of the following methods would help him determine how long this project is likely to take?

group of answer choices
A. pert (program evaluation and review technique)
B. trss (task and resource scheduling system)
C. tpsm (task priority scheduling method)
D. da (dependency analysis)

User Torp
by
7.5k points

1 Answer

6 votes

Final answer:

Sparky can use the a. Pert method to determine the project's duration by analyzing task dependencies and identifying potential delays.

Step-by-step explanation:

To determine how long the project is likely to take, Sparky can use the Pert (Program Evaluation and Review Technique) method. This method involves breaking down the project into individual tasks, estimating the time required for each task, and then determining the critical path, which is the sequence of tasks that will determine the project's overall duration. By using Pert, Sparky can analyze the dependencies between tasks and identify any bottlenecks or potential delays in the project.