The project cost management knowledge area maps to the _____ process group through the activities of estimating costs and budget determination.

a. initiating
b. planning
c. executing
d. monitoring and controlling

User Tdebroc
by
7.3k points

1 Answer

6 votes

Final answer:

The project cost management knowledge area maps to the planning process group.

Step-by-step explanation:

The project cost management knowledge area maps to the planning process group through the activities of estimating costs and budget determination.