Three of the phases of the project lifecycle are Monitoring and Controlling, Planning, and Executing. What is their correct order between Initiating and Closing?

(a) Monitoring and Controlling, Planning, Executing
(b) Planning, Executing, Monitoring and Controlling
(c) Planning, Monitoring and Controlling, Executing
(d) Executing, Monitoring and Controlling, Planning

User Shima
by
7.7k points

1 Answer

3 votes

Final answer:

The correct order between Initiating and Closing for the three mentioned phases of the project lifecycle is Planning, Monitoring and Controlling, Executing.

Step-by-step explanation:

The correct order between Initiating and Closing for the three mentioned phases of the project lifecycle is (c) Planning, Monitoring and Controlling, Executing.

In project management, the project lifecycle consists of several phases that help ensure a structured and organized approach to completing a project. The initiating phase comes first, followed by the planning phase, and then the executing phase. The monitoring and controlling phase occurs after the executing phase and before the closing phase.

  • Initiating: This phase involves defining the project, identifying stakeholders, and stating the project objectives.
  • Planning: This phase involves creating a detailed project plan, including tasks, timelines, resources, and budgets.
  • Executing: This phase involves carrying out the project plan and completing the project deliverables.
  • Monitoring and Controlling: This phase involves tracking the project's progress, monitoring performance, and making adjustments as necessary to ensure the project stays on track.
  • Closing: This phase involves finalizing and delivering the project, conducting a project review, and documenting lessons learned.