Final answer:
Option (b) is NOT true about project management processes. Each process must be performed at least once in a project.
Step-by-step explanation:
Option (b) is NOT true about project management processes. Each process must be performed at least once in a project. This means that every process is necessary and needs to be carried out to successfully complete the project. Skipping any process or neglecting it can lead to incomplete or inefficient project management. Examples of project management processes include project initiation, planning, execution, monitoring, and closing.