Which of the following is NOT a configuration management activity associated with the Perform Integrated Change Control process?

A Configuration identification
B Configuration status accounting
C Configuration risk management
D Configuration verification and auditing

User Ptha
by
7.5k points

1 Answer

2 votes

Final answer:

The correct answer to the question is 'C. Configuration risk management', as it is not a standard activity in configuration management and typically pertains to broader project risk management.

Step-by-step explanation:

The question asks which activity is NOT associated with the Perform Integrated Change Control process in configuration management. The listed activities are:

  • Configuration identification - Establishing and maintaining the consistency of a product's attributes with its requirements and product configuration information.
  • Configuration status accounting - Recording and reporting on the product's configuration and any changes to it.
  • Configuration risk management - NOT a standard activity in configuration management, as it typically falls under broader project risk management.
  • Configuration verification and auditing - Ensuring that the composition of a configuration item is known and that changes to it are systematically controlled.

Therefore, the correct answer to the question is C, Configuration risk management.