Final answer:
The inputs to Perform Integrated Change Control include the project management plan, change requests, and work performance data. Organizational process assets are NOT an input to this process.
Step-by-step explanation:
Perform Integrated Change Control is a process in project management that involves reviewing all change requests, approving and managing those changes, and communicating their status to relevant stakeholders. It ensures that changes are properly evaluated, implemented, and documented.
The inputs to Perform Integrated Change Control include the project management plan, change requests, and work performance data. However, organizational process assets is NOT an input to this process.
Organizational process assets refer to the knowledge, policies, procedures, and historical information accumulated by an organization over time. They can influence how projects are planned, executed, monitored, and controlled, but they are not specifically considered inputs to the Perform Integrated Change Control process.