Final answer:
Organizational process assets updates that are updated as part of the Close Project or Phase process.
Step-by-step explanation:
All of the following are examples of organizational process assets updates that are updated as part of the Close Project or Phase process EXCEPT: Project or phase closure documents. The Close Project or Phase process involves wrapping up all activities and finalizing all deliverables associated with a project or project phase. Some examples of organizational process assets updates that are typically updated during this process include final product, service, or result transition, project files, and historical information. However, project or phase closure documents are not typically updated during this process as they are already considered part of the project closure documentation.