You are in the process of identifying high level risks for your project charter. Which of the following will you not need?

A Enterprise environmental factors, organizational structure
B Risk management plan
C Government standards, industry standards, political climate, marketplace conditions
D Commercial databases

User Sherry
by
8.1k points

1 Answer

1 vote

Final answer:

When identifying high-level risks for a project charter, you will not need Commercial databases. Enterprise environmental factors, organizational structure, risk management plan, and government standards, industry standards, political climate, and marketplace conditions are all important factors to consider in identifying high-level risks for a project.

Step-by-step explanation:

When identifying high-level risks for a project charter, you will not need Commercial databases. When identifying high-level risks for a project charter, you will not need Commercial databases. Enterprise environmental factors, organizational structure, risk management plan, and government standards, industry standards, political climate, and marketplace conditions are all important factors to consider in identifying high-level risks for a project.

Enterprise environmental factors, organizational structure, risk management plan, and government standards, industry standards, political climate, and marketplace conditions are all important factors to consider in identifying high-level risks for a project. Commercial databases are not typically used in this process as they do not directly relate to the identification of risks for a project charter.