Who is responsible for reviewing and approving or rejecting change requests?

A The project manager and project sponsor
B The change control board
C The project sponsor and stakeholders
D The project management office (PMO)

1 Answer

6 votes

Final answer:

The change control board is primarily responsible for reviewing, approving, or rejecting change requests in project management.

Step-by-step explanation:

The entity responsible for reviewing and approving or rejecting change requests in project management is typically The change control board (CCB). This board is often comprised of stakeholders, project managers, and key experts who evaluate the impact of proposed changes on the project’s scope, timeline, and costs. While the project manager may be responsible for initially assessing and facilitating change requests and the project sponsor may have a say in the process, it's the CCB that formally approves or rejects the changes. The PMO might be involved in setting up the change control processes and procedures but does not usually have the authority to approve changes individually unless specifically granted that role on a project.

User Midhun MP
by
8.1k points